November 8, 2017 CUSD BOT Meeting Agenda Item #9 CHANGE ORDER NO. 1, BID NO. 1718-07, CROWN VALLEY ELEMENTARY SCHOOL PORTABLE CLASSROOMS AND RESTROOM PROJECT |
Board Audio: None This Item was passed on Consent without discussion This Item is for work being done on the Crown Valley Elementary School Campus: 01 $17,415.53 Soil Testing requires additional fill and compacting 02 $10,946.90 New Asphalt and slurry seal 03 $ 7,700.74 Modifications to ADA Entrance 04 $3,127.68 New Ramp Transitions on three Modular Buildings moved from Capo Valley High School 05 $ 854.85 Repair and replace water lines atpump 06 $2,795.96 Extend Handrails on new modulars 07 $2,025.88 Clean and pressure wash all blacktop 08 $ 4,894.11 Add new fence behind restroom 09 $1, 297.27 Relocate existing storage shed Total Cost Change Order 01 $51,068.92 Total Cost of Contract with Change Order 01 $319,068.92 Funded by Capital Facilities Fund
|