September 7, 2018 CUSD BOT Meeting Agenda Item #4 CHANGE ORDER NO. 1, BID NO. 1718-12, SAN CLEMENTE HIGH SCHOOL UPPER CAMPUS DEMOLITION PROJECT 

Board Agenda page 209

CUSDWatch Comment

This Agenda Item needs to be amended to reflect 3 Change Orders, Not one.

 

Total Cost to demolish San Clemente High School upper campus building

Original Contract Amount: $498,721.00

Change Order No. 1: $4,126.05 Asbestos Removal

Change Order No. 2: $3,957.01 Asbestos Removal

Did CUSD supply SCAQMD with an emergency letter as required?

Change Order No 3: $19,934.41 Install new drainage pipe

Total Contract Amount with Change Orders: $526,738.47

 

CHANGE ORDER NO 1: $4,126.05

5' of Transite, a known asbestos containing material, was discovered beneath the slab. It will be removed and disposed of per Patriot's work plan.

Asbestos in Transite and Other Building Materials. Originally, the word "transite" was the proprietary brand name of a type of composite siding manufactured by the Johns-Manville Corporation. The original product, introduced in the 1920s, was a mixture of portland cement and asbestos fiber.

Note: CUSD has been aware of Asbestos at San Clemente High School 

CUSDWatch: BOARD ACTION The Board voted 6-0-1 to Ratify Staffs September 8, 2016 response to the Grand Jury's 2015-16 Report On Dealing With Asbestos in Orange County Public Schools.

CUSDWatch: Asbestos Records San Clemente High School

Grand Jury Report: Dealing With Asbestos in Orange County Public Schools

CHANGE ORDER NO 2 $3,957.01

This Change Order REQUIRES CUSD to Supply and Emergency Lletter to SCAQMD. 

Has CUSD done this?

CHANGE ORDER NO. 3 $19,934.41

Excavate and install drainage piping, connect to existing storm drain system, backfill and compact. Drainage was unforeseen as not being in place prior to demo. Pipe was on the east side of the demolished building