Williams Complaint San Juan Hills High School

Complaint Filed November 18, 2017

CUSD has 30 Capistrano Working Days to remedy the Emergency Repairs. 

CUSD must respond to the Complainant within 45 Capistrano Working Days of receipt of the Complaint. CUSD needs to respond by February 11, 2017.

Complainant has 15 days to Appeal CUSD's decision to the CDE if the response is not satisfactory. 

The Appeal must contain a copy of the original complaint to CUSD and a copy of CUSD's decision.

The November 1, 2017 Facilities Condition Assessment San Juan Hills High School Final Report can be found at the following link and is the basis of this complaint:

https://drive.google.com/file/d/0B53sKNZsMg3qVFlwSlFxXzd1QTA/view

This report is 194 pages and documents all facilities issues with pictures.

San Juan Hills High School has $707,100 in EMERGENCY REPAIRS aka conditions that require immediate action to:

a) correct a cited safety hazard,

b) stop accelerated deterioration, and/or

c) return a facility to operation. 

Facilities issues include; but are not limited to:

Roof Construction 5,300
Exterior Walls 300
Horizontal Openings 23,800
Interior Specialities 5,900
Ceiling Finishes  1,800
Cooling Systems 16,500
Electrical Service Distribution 5,100
General Purpose Electrical Power 1,800
Parking Lots 300
Pedestrian Plazas and Walkways 2,800
Site Communication Systems 645,300
TOTAL EMERGENCY REPAIRS $707,100