Williams Complaint San Juan Hills High School | ||||||||||||||||||||||||
Complaint Filed November 18, 2017 CUSD has 30 Capistrano Working Days to remedy the Emergency Repairs. CUSD must respond to the Complainant within 45 Capistrano Working Days of receipt of the Complaint. CUSD needs to respond by February 11, 2017. Complainant has 15 days to Appeal CUSD's decision to the CDE if the response is not satisfactory. The Appeal must contain a copy of the original complaint to CUSD and a copy of CUSD's decision. The November 1, 2017 Facilities Condition Assessment San Juan Hills High School Final Report can be found at the following link and is the basis of this complaint: https://drive.google.com/file/d/0B53sKNZsMg3qVFlwSlFxXzd1QTA/view This report is 194 pages and documents all facilities issues with pictures. San Juan Hills High School has $707,100 in EMERGENCY REPAIRS aka conditions that require immediate action to: a) correct a cited safety hazard, b) stop accelerated deterioration, and/or c) return a facility to operation. Facilities issues include; but are not limited to:
|