Complaint Filed November 16, 2017

CUSD has 30 Capistrano Working Days to remedy the Emergency Repairs. Must Remedy by January 16, 2017.

CUSD must respond to the Complainant within 45 Capistrano Working Days in receipt of Complaint. CUSD needs to respond by February 8, 2017.

Complainant has 15 days to Appeal CUSD's decision to the CDE if the response is not satisfactory. 

The Appeal must contain a copy of the original complaint to CUSD and a copy of CUSD's decision.

 

Williams Complaint Shorecliffs Middle School Capistrano Unified School District  NOVEMBER 15, 2017

The November 1, 2017 Facilities Condition Assessment Shorecliffs Middle School Final Report can be found at the following link and is the basis of this complaint:

https://drive.google.com/file/d/1PUeVUiUAFMOg-3yZSHHR-zCp55RFjp8h/view

This report is 164 pages and documents all facilities issues with pictures.

Shorecliffs Middle School has $3,386,900 in EMERGENCY REPAIRS aka conditions that require immediate action to:

a) correct a cited safety hazard,

b) stop accelerated deterioration, and/or

c) return a facility to operation. 

Facilities issues include; but are not limited to:

Exterior Walls 900
Exterior Doors and Grills 3,800 
Wall Finishes 500 
Domestic Water Distribution 452,000
Sanitary Drainage  53,600
Building Support & Plumbing Systems 8,400
Process Support & Plumbing Systems 50,300
Heating Systems 131,700
Cooling Systems  1,887,600
Facility HVAC Distribution Systems  12,800
Ventilation   8,100
Fire Suppression  4,900
Facility Power Generation  45,300
Electrical Service and Distribution  298,400
General Purpose Electrical Power  2,500
Detection and Alarm  54,200
Residential Equipment  6,400
Roadways  50,300
Pedestrian Plazas and Walkways  1,600
Water Utilities  20,200
Strom Drainage Utilities 11,400
Site Lighting 8,400
Site Communications Systems 2,67,100
TOTAL EMERGENCY REPAIRS $3,386,900